A8 Piding
Early in february NCA received the order to construct the bridge A8 Piding. The weight of one longitudinal girder amounts to 30 tones.
Rubrik:
Bridges
Leistungsumfang:
Construction, transportation and assembly of the steelwork (6x longitudinal girder, 20x cross girder)
Construction, assembly and pre assembly of the shifting track incl. accessories
Futhermore the whole corrosion protection at work and the welding of the field connections
The transportation of the longitudinal girder, cross girder and the parts of the shifting track including the lifting
Kunde:
Hinteregger & Söhne GmbH
Bauherr:
Freistaat Bayern
Architekt/Planer:
Baumann + Obholzer ZT GmbH
Ausführungszeit:
12 month
Eckdaten:
Weight: 250 ton; Material: S235JR+AR - S355JR+AR; Thickness: 8 - 55 mm